ADG provided programming, master planning, and design services for this 55-acre municipal complex. A successful voter referendum provided funding for the development which includes recreation facilities, a city center, and municipal services building, as well as a new police station and improvements to an existing fire station.
The project began with a spatial needs assessment and master plan, and community involvement program conducted by ADG. The completed project was phased to implement the master plan over a two-year construction period.
The first activity was construction of new access roads, parking, and two quadraplex baseball complexes during the six-month league off-season. Next the new municipal building and police facility were built around the existing city hall for continuous operations. The final phase demolished the exiting city hall to create the City Center Plaza that is extensively used for community events. The project was successfully implemented under the value of funds made available by the bond issue from the voter referendum.